New Jersey environmental officials are requiring the Oyster Creek Nuclear Generating Station in Ocean County -- the nation’s oldest nuclear plant -- to install cooling towers. The design change is considered environmentally-friendly, yet costly, and one the plant operators say will force them to shut down.Read moreThe state Department of Environmental Protection is requiring the installation of a "closed-cycle cooling system," which involves mostly air-cooling the plant using one or two towers.
The plant currently cools its system by pumping in about 662 million gallons of water from the Barnegat Bay each day, and pumping in another 748 million additional gallons per day to dilute that heated water before it all is discharged back into the bay, according to Nancy Whittenberg, assistant commissioner for environmental regulation.
Monday, January 11, 2010
Cooling towers required for Oyster Creek nuclear plant may force its closure
From NJ.com:
Subscribe to: