GABI Brief - Project Power: A New U.S.–Korea Nuclear Partnership
The Korean APR 1400 appears to be a worthy partner to the U.S. nuclear industry - repeatedly overly optimistic schedule estimates combined with years of overruns.
The dates listed for each unit are the years in which first concrete placement was started. Six of the reactors are in Korea. The other four were built by the Koreans in the UAE.
Two main points stand out: (1) the actual schedules are much longer than the projected and (2) there doesn't appear to be much of a positive learning curve.
David