NRC OIG Releases Two Reports on Findings Regarding Counterfeit, Fraudulent, and Suspect Items in U.S. Nuclear Power Plants

NRC OIG Releases Two Reports on Findings Regarding
Counterfeit, Fraudulent, and Suspect Items in U.S. Nuclear Power Plants

ROCKVILLE, MD—Today, the Office of the Inspector General (OIG), Nuclear Regulatory Commission (NRC) issued two reports on its audit and investigation findings regarding concerns that counterfeit, fraudulent, and suspect items (CFSI) are present in most, if not all, U.S. nuclear power plants. 

The OIG found that CFSI are present in operating plants, but the extent of CFSI is unknown because the NRC does not require licensees to track CFSI unless a situation rises to the level of being a significant condition adverse to quality, despite concern in the nuclear community about the potential dangers of CFSI. 

The OIG recommended that the NRC should improve its oversight of CFSI by clarifying and communicating how the agency collects, assesses, and disseminates information regarding CFSI, and by improving staff awareness of CFSI and its applicability to reactor inspections.

“The simultaneous issuance of these two reports represents the first time that our Audits and Investigations Divisions have collaborated so closely on a reporting program of this magnitude,” said NRC Inspector General Robert J. Feitel.  “These comprehensive reports are but one example of a new era for the OIG, where our superb teams of auditors and investigators will continue to work together in an integrated way, to fulfill our mission to ensure the integrity, efficiency and effectiveness of the NRC.”

The OIG reports also identified potential gaps in the NRC’s regulatory framework, such as those resulting from a 2011 NRC working group that have since not been resolved. 

The OIG has sent these reports to the NRC’s executive leadership for review and response.  The OIG has a responsibility to independently and objectively conduct audits and investigations to help improve the efficiency and effectiveness of the NRC’s programs and operations.

PR_CFSI_021022.pdf​​​​​​​ 

Thursday, February 17, 2022

Exelon SPIN: Commission Memorandum and Order (CLI-22-01)

In the Matter of
​​​​​​​
EXELON GENERATION COMPANY, LLC;
EXELON CORPORATION; EXELON
FITZPATRICK, LLC; NINE MILE POINT
NUCLEAR STATION, LLC; R.E. GINNA
NUCLEAR POWER PLANT, LLC; and
CALVERT CLIFFS NUCLEAR POWER
PLANT, LLC

E220214t015923_CLI-22-01 Final Order.pdf

Thursday, February 10, 2022

Peach Bottom Atomic Power Station, Units 2 and 3 - Integrated Inspection Report 05000277/2021004 and 05000278/2021004

SUBJECT: PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 – INTEGRATED INSPECTION REPORT 05000277/2021004 AND 05000278/2021004

Monday, February 7, 2022

Technical Review: TMI's Request for Water to Cleanup Nuclear Plants, (TMI-Alert, 1/3/22) -- SRBC RESPONSE - DOCUMENTS ATTACHED

TMI's Request for Water to Cleanup Nuclear Plants, (TMI-Alert, 1_3_22).pdf

Exelon - Three Mile Island (2021-054, 2021-055, 2021-056) Response Letter to Eric Epstein on 1-3-22 Comments 02-04-2022.PDF

Constellation Energy Generation, LLC - Issuance of Amendments Related to Order Approving Transfer of Licenses

Subject:  Braidwood, Byron, Calvert Cliffs, Clinton, Dresden, FitzPatrick, LaSalle, Limerick, Nine Mile, Peach Bottom, Quad Cities, Ginna, Salem, Three Mile - Issuance of Amendments Related to Order Approving Transfer of Licenses (EPID L-2022-LLM-0000) (Letter)

ADAMS Accession No.:  ML22021B659


Using Web-based ADAMS, select “Advanced Search”
Under “Property,” select “Accession Number”
Under “Value,” enter the Accession Number
Click Search 


Subject:  Braidwood, Byron, Calvert Cliffs, Clinton, Dresden, FitzPatrick, LaSalle, Limerick, Nine Mile, Peach Bottom, Quad Cities, Ginna, Salem, Three Mile - Issuance of Amendments Related to Order Approving Transfer of Licenses (EPID L-2022-LLM-0000) - Enclosure 1

ADAMS Accession No.:  ML22021B660