SUSQUEHANNA STEAM ELECTRIC STATION – NRC INTEGRATED INSPECTION REPORT 05000387/2013002 AND 05000388/2013002
Download PDF
Tuesday, May 14, 2013
Peach Bottom Atomic Power Station, Units 2 and 3 - Transmittal of Draft Safety Evaluation
PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 TRANSMITTAL OF
DRAFT SAFETY EVALUATION FOR PROPOSED AMENDMENT RE: USE OF NEUTRON
ABSORBING INSERTS IN SPENT FUEL POOL STORAGE RACKS (TAC NOS. ME7538 AND
ME7539)
Download ML13121A288
Download ML13121A288
Duke Suspends Effort to License Nuclear Units; NRC Shoot s Down Texas Nuclear Plant Expansion
Duke Energy Suspends Effort to License North Carolina Nuclear Units:
Reuters, May 2, 2013
http://mobile.reuters.com/article/idUSL2N0DJ2QG20130502?irpc=932
Duke Energy, the largest U.S. electric utility, says it has notified regulators that it will drop plans to build two new nuclear reactors in North Carolina due to slow growth in power demand. Progress Energy, which Duke acquired last year, proposed building two AP1000 reactors at the Harris nuclear plant site in Wake County, North Carolina, and submitted an application in 2008 for a construction and operating license from the U.S. Nuclear Regulatory Commission. The company's supply forecast indicates additional nuclear generation won't be needed at Harris for at least 15 years. However, Duke said it will continue to work to obtain NRC licenses for two new reactors in Levy County, Florida, and another two reactors in Gaffney, South Carolina. Four new reactors are currently under construction at two sites in the southeastern United States: two at Scana Corp's Summer nuclear station in South Carolina and two at Southern Co's Vogtle station in Georgia.
======================================
NRC Shoots Down Texas Nuclear Plant Expansion Citing Too Much Foreign Ownership:
Dallas News, by James Osborne, April 30, 2013
http://bizbeatblog.dallasnews.com/2013/04/nrc-shoots-down-texas-nuclear-plant-expansion.html and
San Antonio Express-News, by Nolan Hicks, April 30, 2013
http://nukefreetexas.org/2013/05/regulators-too-much-foreign-ownership-for-nuclear-expansionPlans to build two new reactors at the South Texas Project nuclear facility outside Bay City have hit a road block. The U.S. Nuclear Regulatory Commission ruled that a partnership between NRG and Toshiba Corp. through the holding company Nuclear Innovation North America violated a U.S law prohibiting foreign control of nuclear power plants. The holding company plans to appeal the ruling to the NRC’s Atomic Safety Licensing Board, arguing that NRG controls 90 percent of the holding company, a NRG spokesman said. NRG and Toshiba remain hopeful they can convince the atomic safety board to overrule NRC staff. But they will likely face an uphill climb. No date for a hearing has been set.
Reuters, May 2, 2013
http://mobile.reuters.com/article/idUSL2N0DJ2QG20130502?irpc=932
Duke Energy, the largest U.S. electric utility, says it has notified regulators that it will drop plans to build two new nuclear reactors in North Carolina due to slow growth in power demand. Progress Energy, which Duke acquired last year, proposed building two AP1000 reactors at the Harris nuclear plant site in Wake County, North Carolina, and submitted an application in 2008 for a construction and operating license from the U.S. Nuclear Regulatory Commission. The company's supply forecast indicates additional nuclear generation won't be needed at Harris for at least 15 years. However, Duke said it will continue to work to obtain NRC licenses for two new reactors in Levy County, Florida, and another two reactors in Gaffney, South Carolina. Four new reactors are currently under construction at two sites in the southeastern United States: two at Scana Corp's Summer nuclear station in South Carolina and two at Southern Co's Vogtle station in Georgia.
======================================
NRC Shoots Down Texas Nuclear Plant Expansion Citing Too Much Foreign Ownership:
Dallas News, by James Osborne, April 30, 2013
http://bizbeatblog.dallasnews.com/2013/04/nrc-shoots-down-texas-nuclear-plant-expansion.html and
San Antonio Express-News, by Nolan Hicks, April 30, 2013
http://nukefreetexas.org/2013/05/regulators-too-much-foreign-ownership-for-nuclear-expansionPlans to build two new reactors at the South Texas Project nuclear facility outside Bay City have hit a road block. The U.S. Nuclear Regulatory Commission ruled that a partnership between NRG and Toshiba Corp. through the holding company Nuclear Innovation North America violated a U.S law prohibiting foreign control of nuclear power plants. The holding company plans to appeal the ruling to the NRC’s Atomic Safety Licensing Board, arguing that NRG controls 90 percent of the holding company, a NRG spokesman said. NRG and Toshiba remain hopeful they can convince the atomic safety board to overrule NRC staff. But they will likely face an uphill climb. No date for a hearing has been set.
Peach Bottom Atomic Power Station - NRC Integrated Inspection Report 05000277/2013002 and 05000278/2013002
Peach Bottom Atomic Power Station - NRC Integrated Inspection Report 05000277/2013002 and 05000278/2013002
Download PDF
Download PDF
Electric Power Research Institute Final Draft Report XXXXXX, “Seismic Evaluation Guidance: Augmented Approach for the Resolution of Fukushima Near-Term Task Force Recommendation 2.1: Seismic”
Electric Power Research Institute Final Draft Report XXXXXX, “Seismic
Evaluation Guidance: Augmented Approach for the Resolution of Fukushima
Near-Term Task Force Recommendation 2.1: Seismic,” As an Acceptable
Alternative to the March 12, 2012, Information Request for Seismic
Reevaluations
Download ML13106A331
Download ML13106A331
Thursday, May 9, 2013
Nuclear Hot Spots Map for the Great Lakes released today
|
Monday, May 6, 2013
NRC Seeks Public Comment on Proposed Changes to Petition-for-Rulemaking Process
NRC Seeks Public Comment on Proposed Changes to Petition-for-Rulemaking Process
The Nuclear Regulatory Commission is seeking public comment on a proposal to streamline and clarify its process for addressing petitions for rulemaking. Proposed changes to that process, to be published in the May 3 Federal Register, aim to improve transparency and make the process more efficient and effective.
Download PDF
The Nuclear Regulatory Commission is seeking public comment on a proposal to streamline and clarify its process for addressing petitions for rulemaking. Proposed changes to that process, to be published in the May 3 Federal Register, aim to improve transparency and make the process more efficient and effective.
Download PDF
Subscribe to:
Posts (Atom)