Even if Vermont Yankee nuclear plant shuts down in 2012 when its original federal license expires, Entergy Nuclear wouldn't start cleaning up and dismantling the reactor for close to 60 years, according to a plan filed with the Nuclear Regulatory Commission. Entergy Nuclear has agreed to add $60 million to its shrinking decommissioning fund for the Vermont Yankee nuclear plant — but not until 2026. In its filing with the Nuclear Regulatory Commission, Entergy Nuclear said it planned on decommissioning the reactor in 2067, and completing the job by 2072, at a total cost of $875 million.