Acceptance Review of LAR To Revise the Dose Consequence Analysis For A Loss Of Coolant Accident (EPID L-2020-LLA-0000)
ADAMS Accession No. ML20028F635
ML20028F635.pdf
Thursday, January 30, 2020
Tuesday, January 28, 2020
Three Mile Island Nuclear Station, Unit 1 – Withdrawal of Order EA-12-051, “Order Modifying Licenses With Regard to Reliable Spent Fuel Pool Instrumentation” (EPID L-2019-JLD-0019)
Three Mile Island Nuclear Station, Unit 1 – Withdrawal of Order EA-12-051, “Order Modifying Licenses With Regard to Reliable Spent Fuel Pool Instrumentation” (EPID L-2019-JLD-0019)
ADAMS Accession No. ML19318E476
ML19318E476.pdf
ADAMS Accession No. ML19318E476
ML19318E476.pdf
Monday, January 27, 2020
TMI 1 - Withdrawal of Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events" (EPID L-2019-JLD-0018) Primary
Three Mile Island Nuclear Station, Unit 1 - Withdrawal of Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events" (EPID L-2019-JLD-0018)
ADAMS Accession No. ML19318E145
ML19318E145.pdf
ADAMS Accession No. ML19318E145
ML19318E145.pdf
Thursday, January 16, 2020
Susquehanna Steam Electric Station, Units 1 and 2 - Issuance of Amendment Nos. 274 and 256 to Revise Shutdown Margin Definition to Address Advanced Fuel (TSTF-535, Revision 0) (EPID L-2019-LLA-0154)
Susquehanna Steam Electric Station, Units 1 and 2 - Issuance of Amendment Nos. 274 and 256 to Revise Shutdown Margin Definition to Address Advanced Fuel (TSTF-535, Revision 0) (EPID L-2019-LLA-0154)
Wednesday, January 15, 2020
PA DEP News Release : Students Encourage Pennsylvanians to Start Year Off Radon Safe with Simple Home Test
DEP Newsroom
COMMONWEALTH OF PENNSYLVANIA
Dept. of Environmental Protection
Commonwealth News Bureau
Room 308, Main Capitol Building
Harrisburg PA., 17120
Dept. of Environmental Protection
Commonwealth News Bureau
Room 308, Main Capitol Building
Harrisburg PA., 17120
FOR IMMEDIATE RELEASE
01/6/2020
CONTACT:
Deb Klenotic, DEP
717-783-9954
Nate Wardle, DOH
717-346-4704
Harrisburg, PA – Students at Dingman-Delaware Middle School in Pike County are helping to encourage Pennsylvanians to do a simple home test for radon in January, National Radon Action Month. This invisible, odorless, naturally occurring radioactive gas is the second leading cause of lung cancer.
Radon occurs from the breakdown of uranium in the ground. It enters homes through cracks in the foundation or other openings.
“Because of Pennsylvania’s geology, there are high radon levels in locations around the state, putting residents at risk of exposure,” said Department of Environmental Protection (DEP) Secretary Patrick McDonnell. “Fortunately, it’s simple to determine the radon level in your home using an inexpensive test.”
PA DEP News Release : DEP Issues Historic $30.6 Million Penalty Over Revolution Pipeline Violations
DEP Newsroom
COMMONWEALTH OF PENNSYLVANIA
Dept. of Environmental Protection
Commonwealth News Bureau
Room 308, Main Capitol Building
Harrisburg PA., 17120
Dept. of Environmental Protection
Commonwealth News Bureau
Room 308, Main Capitol Building
Harrisburg PA., 17120
FOR IMMEDIATE RELEASE
01/3/2020
CONTACT:
Elizabeth Rementer, DEP
717-787-1323
Department Collects One of the Largest Civil Penalties in Single Settlement History
Harrisburg, PA – The Pennsylvania Department of Environmental Protection (DEP) today announced that it has issued a $30.6 million civil penalty to ETC Northeast Pipeline (ETC) for violations related to the 2018 Revolution Pipeline explosion and fire. The penalty is one of the largest civil penalties collected in a single settlement.
“ETC’s lack of oversight during construction of the Revolution Pipeline and their failure to comply with DEP’s October 2018 compliance order demanded serious accountability. Their inaction led directly to this unprecedented civil penalty,” said DEP Secretary Patrick McDonnell. “DEP is committed to holding permittees accountable for permit compliance and will continue to provide active and stringent oversight over the construction of their projects. Permittees are obligated to ensure that their projects are constructed without incident and in full compliance with permits. If a permittee fails to do so, they will be held accountable.”
Thursday, January 9, 2020
Braidwood 1 and 2, Byron 1 and 2, Calvert Cliffs 1 and 2, Clinton 1, Dresden 1, 2, and 3, FitzPatrick, LaSalle 1 and 2, Limerick 1 and 2, Nine Mile 1 and 2, Peach Bottom 1, 2 and 3, Quad Cities 1 and 2, and Ginna - Review of Quality Assurance Program Changes (EPID L-2019-LLQ-0003) ADAMS Accession No. ML19350A830
Braidwood 1 and 2, Byron 1 and 2, Calvert Cliffs 1 and 2, Clinton 1, Dresden 1, 2, and 3, FitzPatrick, LaSalle 1 and 2, Limerick 1 and 2, Nine Mile 1 and 2, Peach Bottom 1, 2 and 3, Quad Cities 1 and 2, and Ginna - Review of Quality Assurance Program Changes (EPID L-2019-LLQ-0003)
ADAMS Accession No. ML19350A830
Exelon_ML19350A830.pdf
ADAMS Accession No. ML19350A830
Exelon_ML19350A830.pdf
Wednesday, January 8, 2020
Susquehanna Steam Electric Station – NRC Investigation Report No. 1-2018-011 and Notice of Violation
Susquehanna Steam Electric Station – NRC Investigation Report No. 1-2018-011 and Notice of Violation
ADAMS Accession No. ML20007D652
Subscribe to:
Posts (Atom)