Thursday, May 8, 2025

"It wasn't secret. It was confidential," Marsh said.

https://www.foxbusiness.com/markets/attorney-utilities-meant-to-hide-report-on-nuclear-project

Attorney: Utilities meant to hide report on nuclear project

By SEANNA ADCOX Associated Press


For at least two years before a South Carolina nuclear power construction project was abandoned, its owners had a report that they intended to keep secret showing the reactors couldn't be completed as planned, an attorney for a legislative panel investigating the debacle said Friday.

"The report is very, very troubling," said Scott Elliott, hired by the House for the hearings.  "It was designed to never see the light of day."

State-owned Santee Cooper and South Carolina Electric & Gas hired Bechtel Corp. in 2015 to assess construction on two new reactors at V.C. Summer Nuclear Station north of Columbia.  The utilities were briefed on the findings later that year, though the official report is dated February 2016.

Essentially, the report says "this wasn't going to work. ... If things don't change dramatically, you'll never finish these projects," Elliott said.  Its findings included a lack of proper oversight by SCE&G, the majority owner.

SCE&G should have disclosed the report's existence as it successfully sought approval in 2015 and 2016 to spend more on the project.  Instead, executives told state regulators they were confident in the presented completion dates, said Elliott, also an attorney for South Carolina Energy Users Committee, a coalition of large industries that need a lot of energy.

Legislators accused SCE&G executives of intentionally hiding the report from regulators and lawmakers, withholding information that could have resulted in "no" votes.

Kevin Marsh, CEO of SCE&G's parent company SCANA, told legislators the report was confidential because it was intended to be used in a potential lawsuit against the site's main contractor, Westinghouse.

"It wasn't secret.  It was confidential," Marsh said.

The utilities abandoned the project July 31 after jointly spending nearly $10 billion, leaving nearly 6,000 people jobless.  A 2007 state law allows SCE&G to recoup its debt from customers if state regulators determine money was spent prudently.

Legislators who are seeking ways to fix the law want to stop that.  Customers have already paid more than $2 billion on interest costs through a series of rate hikes since 2009.  The project accounts for 18 percent of SCE&G customers' electric bills.

Elliott said the Bechtel report puts into question every decision made by the utilities over at least the last two years.

But Marsh continued Friday to blame the project's failure on Westinghouse's bankruptcy in March, which voided a fixed-price contract negotiated in 2015 in an attempt to control costs.  And he insisted the utility did nothing wrong, and no one deserved to be fired.

"Did we make any mistakes?  A project this large, you're going to make some mistakes," he said.  "I don't think we made any material mistakes to change the outcome of where we are today."

He said the report's findings only highlighted what the utilities knew.  SCANA chief operating officer Steve Byrne said the fixed-price contract addressed many of the budgeting concerns.

"It was mostly to validate our concerns rather than tell us something we didn't know," Marsh said.  "I believe we acted appropriately and prudently."

The Bechtel report's existence became public as executives testified at a legislative hearing last month.  Lawmakers threatened to subpoena it if the utilities refused to provide it.  Gov. Henry McMaster released it to reporters earlier this month, over SCANA's written objections, after receiving a copy from Santee Cooper.

Rep. James Smith, D-Columbia, told Marsh SCANA needs to acknowledge its share of the blame.

House Minority Leader Todd Rutherford, D-Columbia, said executives' testimony shows they "just don't get it.”

Google agrees to fund the development of three new nuclear sites

Google agrees to fund the development of three new nuclear sites

Pippa Stevens @PippaStevens13

  • Nuclear developer Elementl Power said Wednesday it’s signed an agreement with Google to develop three project sites for advanced reactors.
  • Google will commit early-stage development capital to the three projects, each of which will generate at least 600 megawatts.
  • It’s the latest example of tech giants teaming up with the nuclear industry in an effort to meet the vast energy needs of data centers. 
 

NRC Makes Available Partial Construction Permit Application for TVA's Clinch River Small Modular Reactor

Nuclear Regulatory Commission - News Release
No: 25-026 May 5, 2025
CONTACT: Maureen Conley, 301-415-8200

NRC Makes Available Partial Construction Permit Application for TVA's Clinch River Small Modular Reactor


The Nuclear Regulatory Commission has received the first portion of a construction permit application from Tennessee Valley Authority for a GE-Hitachi BWRX-300 small modular reactor at the Clinch River Nuclear Site in Oak Ridge, Tennessee. The application is now available for public inspection on the NRC website.

TVA submitted the environmental report portion of the application on April 28. The BWRX-300 design would generate approximately 300 megawatts of electricity, using boiling-water reactor technology. TVA would have to submit an additional application in the future for permission to operate the facility.

NRC staff are reviewing the environmental report to determine if it is complete and acceptable for processing. If the partial application is determined to be sufficient, the staff will docket it and start a detailed technical review.

The NRC understands TVA plans to file the second portion of the Clinch River application, a preliminary safety analysis report, in several weeks. The NRC will perform an acceptance review for that report at that time. If both portions are accepted for review, the NRC will then publish a notice of opportunity to request an adjudicatory hearing on the application before the NRC's Atomic Safety and Licensing Board.

Information about TVA's Clinch River project is available on the NRC website.

Monday, May 5, 2025

Rat Infestation Disrupts UK Nuclear Plant Construction

FYI... Just saying... Rat Infestation Disrupts UK Nuclear Plant Construction

https://www.baystreet.ca/commodities/7919/Rat-Infestation-Disrupts-UK-Nuclear-Plant-Construction


Rat Infestation Disrupts UK Nuclear Plant Construction

The U.K. has ambitious nuclear power plans and is developing several small- and large-scale projects. While opposition, high costs, and other factors have slowed development in the past, EDF has ...

www.baystreet.ca

image.png

Tuesday, April 29, 2025

Crane Clean Energy Center/Three Mile Island Nuclear Station, Unit 1 Restart Inspection Plan

Crane Clean Energy Center/Three Mile Island Nuclear Station, Unit 1 Restart Inspection Plan
ADAMS Accession No. ML25114A121

Monday, April 28, 2025

"It wasn't secret. It was confidential," Marsh said.

https://www.foxbusiness.com/markets/attorney-utilities-meant-to-hide-report-on-nuclear-project

Attorney: Utilities meant to hide report on nuclear project

By SEANNA ADCOX Associated Press


For at least two years before a South Carolina nuclear power construction project was abandoned, its owners had a report that they intended to keep secret showing the reactors couldn't be completed as planned, an attorney for a legislative panel investigating the debacle said Friday.

"The report is very, very troubling," said Scott Elliott, hired by the House for the hearings.  "It was designed to never see the light of day."

State-owned Santee Cooper and South Carolina Electric & Gas hired Bechtel Corp. in 2015 to assess construction on two new reactors at V.C. Summer Nuclear Station north of Columbia.  The utilities were briefed on the findings later that year, though the official report is dated February 2016.

Essentially, the report says "this wasn't going to work. ... If things don't change dramatically, you'll never finish these projects," Elliott said.  Its findings included a lack of proper oversight by SCE&G, the majority owner.

SCE&G should have disclosed the report's existence as it successfully sought approval in 2015 and 2016 to spend more on the project.  Instead, executives told state regulators they were confident in the presented completion dates, said Elliott, also an attorney for South Carolina Energy Users Committee, a coalition of large industries that need a lot of energy.

Legislators accused SCE&G executives of intentionally hiding the report from regulators and lawmakers, withholding information that could have resulted in "no" votes.

Kevin Marsh, CEO of SCE&G's parent company SCANA, told legislators the report was confidential because it was intended to be used in a potential lawsuit against the site's main contractor, Westinghouse.

"It wasn't secret.  It was confidential," Marsh said.

The utilities abandoned the project July 31 after jointly spending nearly $10 billion, leaving nearly 6,000 people jobless.  A 2007 state law allows SCE&G to recoup its debt from customers if state regulators determine money was spent prudently.

Legislators who are seeking ways to fix the law want to stop that.  Customers have already paid more than $2 billion on interest costs through a series of rate hikes since 2009.  The project accounts for 18 percent of SCE&G customers' electric bills.

Elliott said the Bechtel report puts into question every decision made by the utilities over at least the last two years.

But Marsh continued Friday to blame the project's failure on Westinghouse's bankruptcy in March, which voided a fixed-price contract negotiated in 2015 in an attempt to control costs.  And he insisted the utility did nothing wrong, and no one deserved to be fired.

"Did we make any mistakes?  A project this large, you're going to make some mistakes," he said.  "I don't think we made any material mistakes to change the outcome of where we are today."

He said the report's findings only highlighted what the utilities knew.  SCANA chief operating officer Steve Byrne said the fixed-price contract addressed many of the budgeting concerns.

"It was mostly to validate our concerns rather than tell us something we didn't know," Marsh said.  "I believe we acted appropriately and prudently."

The Bechtel report's existence became public as executives testified at a legislative hearing last month.  Lawmakers threatened to subpoena it if the utilities refused to provide it.  Gov. Henry McMaster released it to reporters earlier this month, over SCANA's written objections, after receiving a copy from Santee Cooper.

Rep. James Smith, D-Columbia, told Marsh SCANA needs to acknowledge its share of the blame.

House Minority Leader Todd Rutherford, D-Columbia, said executives' testimony shows they "just don't get it."

"At what point does the person paying these bills get some relief?  They can't opt out.  Their only way out is to move," said Rep. Kirkman Finlay, R-Columbia.  "How is this acceptable?  I don't think there's anything you can say that makes sense.  Spending $30 million a week is prudent?"