Citizens Awareness Network
Nuclear Information and Resource Service
Secretary
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001
ATTN: Rulemakings and Adjudications Staff
Comments
on Nuclear Regulatory Commission Request Advanced Notice of Proposed
Rulemaking Regarding Regulatory Improvements for Decommissioning Power
Reactors
Jointly Submitted by Citizens Awareness Network and Nuclear Information and Resource Service
The
following are comments jointly submitted by Citizens Awareness Network
and Nuclear Information and Resource Service, in response to the Draft
Regulatory Guide Docket ID NRC-2015-0070 request for comments on the
advanced notice of proposed rulemaking regarding decommissioning of
nuclear power reactors, published November 19, 2015. A hard copy will
follow in the mail.
NRC’s attempt to streamline the
decommissioning process instituted in the wake of the Yankee Rowe
decommissioning and the Appellate Court Decision in CAN v NRC undermines
the ability for the public or the state to participate in matters that
vitally affect them. It also undercuts the Agency’s ability to
effectively regulate the cleanup of contaminated sites. The First
Circuit Appellate Court found the decommissioning of Yankee Rowe illegal
and in violation of the National Environmental Policy Act, the
Administrative Procedures Act and the Atomic Energy Act. NRC’s response
to the Court’s reprimand was to codify its actions in Rowe and
effectively deregulate decommissioning. The agency’s own Inspector
General’s Report, NRC at a Crossroads, underscored the radical shift
that NRC proposed and codified in 1996 (61 FR39278; July 29, 1996).
NRC
is now proposing another radical shift in policy and regulation. Its
decision to focus on the vulnerability of reactor fuel pools and dry
cask storage as the sole priority for agency regulation of
decommissioning abdicates its responsibility to impacted communities and
states. The management and security of high-level radioactive waste is
not formally part of the decommissioning process, it is covered by
distinct and separate regulations. While the transfer of irradiated fuel
from spent fuel pools to dry-cask storage facilities is necessary to
complete decommissioning, license termination for the reactor ownership
license may proceed separately under decommissioning, converting to a
high-level waste storage license for the remaining dry- cask storage
facility. This separation of decommissioning and high-level waste
management is also evident in the NRC’s decommissioning funding
assurance regulation, which does not include high-level waste costs in
the calculation of minimum decommissioning funding assurance
requirements.
NRC’s assertion in the Advance Notice of
Proposed Rulemaking that the purpose of NRC rulemaking in regard to
decommissioning is to manage the level of “radiological risk compared to
operating reactors” is completely and utterly misinformed. The purpose
of decommissioning is to facilitate the safe dismantlement of the
nuclear reactor facilities and remediation of the site to permit its
release to unrestricted use by the public, which entails reduction of
risk to the public from long-term exposure to radioactive materials
produced and deposited on the site as a result of the licensed
activities that took place there. The license termination step, which
concludes the decommissioning process, is to ensure that licensees are
held accountable for satisfying the objectives of radiological
decommissioning and site remediation and the promises made to reactor
communities when the facilities were sited and licensed by NRC. The
purpose of radiological risk reduction from irradiated fuel storage is
covered by high-level waste regulations.
The intent suggested
in the ANPR to scale back NRC oversight and involvement in the
decommissioning process forecasts an abdication of regulatory authority
and negligence toward the agency’s mandate to protect the public health
and safety. To the extent that the regulatory analysis presented in the
ANPR will structure the NRC’s proposed revisions to decommissioning
regulations, it must be abandoned and a new course set. That course must
be to address the proven experience and emerging problems confronting
the protection of the public health and safety and achievement of the
aforementioned purposes of decommissioning.
The primary focus
of decommissioning must remain site remediation and restoration. Spent
fuel management is a separate regulatory concern; it should not be
solved by relegating decommissioning ratepayer subsidization of interim
solution for HLW. By determining that cleanup of radiologically
contaminated sites poses no risk to the public, NRC’s attempts to
justify this radical rewriting of its rules. This is unacceptable.
Again, risk was not the issue in decommissioning, site remediation and
license termination were. The comments provided below are directed
toward revising the decommissioning regulations for those purposes.
NRC MUST REQUIRE LICENSEES TO HAVE FULLY FUNDED DECOMMISSIONING FUNDS UPON CLOSURE.
Decommissioning
trust funds for reactor cleanup are notoriously underfunded. The NRC
permitsnuclear corporations to seriously under-fund their
decommissioning funds with the rationale that, over time and with the
ability for shuttered reactors to remain in SAFSTOR for up to 60 years,
the funds required for cleanup will accumulate eventually. In addition,
under utility owned nuclear facilities, utilities could request rate
increases from state public service entities to cover any shortfalls in
the fund. This was certainly the case at Yankee Rowe and Connecticut
Yankee. These captured ratepayers covered the substantial shortfalls for
inadequate and incompetent financial planning. With NRC’s approval of
merchant fleets of nuclear reactors, no captive ratebase exists to
subsidize inadequate planning by licensees; contaminated sites can
languish for indeterminate periods of time with no surety that the
corporation responsible for cleanup will exist in 60 years. This
undermines the impacted community as well as the states that remain in
part responsible to represent ratepayers as well as state interests.
DECOMMISSIONING
FUNDS CAN ONLY BE USED FOR RADIOLOGICAL CLEANUP. NO EXEMPTIONS TO
PERMIT ACCESS TO THE DECOMMISSIONING FUND FOR OTHER PURPOSES.
The
decommissioning funding assurance regulation (10 CFR Part 50.75) was
established to ensure licensees possess the resources for the cleanup of
radiological contamination at reactor sites. Its express purpose is to
permit the site to be released for unrestricted use (if possible) after
cleanup is completed. However, NRC has permitted licensees, through an
exemption process, to substantially undermine the financial viability of
the trust funds by permitting their use for non- radiological purposes.
For example Entergy Nuclear Vermont Yankee, LLC (ENVY), has advanced a
series of propositions for the use of Vermont Yankee’s decommissioning
fund that have nothing to do with radiological cleanup. However, these
appropriations have everything to do with Entergy’s corporate structure,
the licensee’s financial vulnerability and its lack of adequate
operational funds. With NRC approval, Entergy intends to use
decommissioning funds to pay its $600,000 in local taxes, its legal as
well as lobbying expenses, its costs for fuel transfer from the fuel
pool to dry cask storage , as well as for guarding the high level waste
installation through the 2050’s. Permitting these withdrawals is
unacceptable; it seriously undermines the fund and substantially delays
radiological cleanup. NRC should institute a process to hold parent
companies accountable for the financial shortfalls of their LLCs.
NRC’s
regulatory posture toward the use of decommissioning funds undermines
state’s interests in ensuring a timely, safe, and effective
decommissioning, and creates a massive subsidy to the industry at the
expense of taxpayers and utility ratepayers. States permitted utilities
to charge their customers for the cost of decommissioning trust fund
contributions because those ratepayers benefited from the power
generated by nuclear reactors. Now, the NRC is effectively allowing
licensees to profiteer from a failed nuclear waste policy, on the backs
of ratepayers and taxpayers: that is, the inability to implement a
solution for its high level waste problem through the establishment of a
nuclear waste dump by 1998, as required by the Nuclear Waste Policy
Act. By granting exemptions from decommissioning trust fund regulations,
NRC is now permitting nuclear reactor licensees with inadequate
financial resources to raid the decommissioning fund for not just the
establishment of dry cask storage, but, even more significantly, for the
guarding of the waste on site.
Through suing DOE for this
failure under the Nuclear Waste Policy Act, the industry has been able
to win settlements reimbursing the corporations for the transfer of
irradiated fuel from spent fuel pools to dry-cask storage (with
settlements amounting to about 80% of the licensees’ claimed expenses).
Despite permitting licensees exemptions from decommissioning trust fund
regulations in order to access the trust funds for fuel transfer
expenses, NRC has not required licensees to reimburse the trust funds
with the settlement proceeds. This practice constitutes a massive
misappropriation of decommissioning funds by allowing licensees’ parent
companies to profit from the decommissioning funds. More importantly, it
compromises public health and safety by justifying delays in the
conduct of decommissioning and site remediation activities for
potentially decades (through licensees’ exercise of the SAFSTOR option),
until trust funds have accumulated sufficient value to cover
radiological decommissioning costs.
In addition, high-level
waste lawsuit settlements will not cover the escalating costs of
guarding spent fuel storage installations, which could carry on
indefinitely, as recognized by the NRC’s recently promulgated continued
storage rule. NRC’s practice of granting licensees exemptions to access
trust funds for that and other non-decommissioning purposes – such as
local property taxes – exacerbates the risks to public health and safety
and increases the subsidy to licensees, their parent companies and
shareholders at states’ expense. It will not only further delay
decommissioning and site remediation, but runs the risk of depleting
decommissioning funds to the point that decommissioning cannot be
completed with the available trust fund balances. NRC has not adequately
addressed the issue of parent company liability for decommissioning,
site remediation, and, ultimately, license termination under new
corporate ownership structures that prevail today in the use of limited
liability corporations (LLCs) as the sole possessors of the ownership
licenses.
Under these circumstances, the existing regulations
and NRC’s current regulatory practices could well result in financial
liability for decommissioning falling to ratepayers and/or taxpayers to
subsidize nuclear licensees’ lack of sufficient financial resources to
protect and remediate their own sites, with parent companies protected
from ultimate liability through the LLC ownership structure. Instead,
NRC should both prohibit the use of decommissioning funds for non-
decommissioning purposes and require parent companies to serve as
co-licensees. In addition, NRC should require licensees to establish
separate or auxiliary funds for other regulated activities, including
the storage and management of high-level waste. Should the federal
government implement a long-term management solution before such funds
were fully expended, excess monies could be returned to the licensee.
NRC SHOULD RESTORE NATIONAL ENVIRONMENTAL POLICY ACT COMPLIANCE.
Decommissioning
should be reclassified as a Major Federal Action requiring NEPA
compliance and the participation of the EPA in decommissioning. Cleaning
up highly contaminated sites requires significant oversight. It should
not be driven by licensees or their lack of adequate funding. The First
Circuit Appellate Court justices opined in CAN v NRC that
decommissioning is a major federal action and requires NEPA compliance.
“An agency cannot skirt NEPA or other statutory commands by exempting a
licensee from compulsory compliance, and then simply labeling its
decision “mere oversight” rather than a major federal action. To do so
is manifestly arbitrary and capricious.” NEPA compliance was required
and mandated by the court for decommissioning. Doing so would reinstate
the use of NRC resident inspectors and increase NRC oversight and public
participation. It would reinstate EPA oversight beyond ground water
contamination to address the significant chemical contamination at
decommissioning sites. It could also support the requirement for an
Emergency Planning Zone (EPZ) until the high level nuclear waste is
transferred from high-density pool storage and secured in dry cask
storage.
It is essential for NRC to define decommissioning as a
major federal action. As the Appellate Court opined “… it is undisputed
that decommissioning is an action which, even under the Commission’s
new policy, requires NEPA compliance 10 C.F.R. 51.95(b.).” The Agency’s
choice to streamline the process for licensees and deregulate NRC
requirements abdicated the agency’s responsibility to protect the health
and safety of the workers, the public, the environment, and also
undermines citizen due process.
NRC SHOULD RESTORE ALL DECOMMISSIONING SAFEGUARDS INCLUDING THE HEARING RIGHTS OF THE PUBLIC.
NRC’s
radical 1996 revision of the decommissioning regulation eviscerated the
hearing rights of the public, as well as states. Public meetings do not
constitute the hearing rights required by the Atomic Energy Act and
affirmed in CAN v. NRC. Adjudicatory hearings offer citizens the right
to cross examination and discovery. A public meeting does not afford
citizens the level of institutional accountability necessary given the
dangers of enviro-toxic contamination inherent in the cessation of
reactor operations. Informational meetings, as experienced at
Yankee-Rowe, Connecticut Yankee and Vermont Yankee, do not effectively
address the concerns of local residents since the local community --
and, for that matter, states -- have no power to effect change in the
licensee’s choices. In CAN v.
NRC, both the Federal District Court and
the Appellate Court chastised the agency for this approach. If the
community has concerns, and there is no regulatory recourse save one
"meeting" with NRC, the Commission will, in fact, create greater
polarization between the community and the regulator. This can lead to
intensified mistrust of the agency and further costly legal battles as
is seen in the decommissioning of Vermont Yankee. Advisory boards, such
as Vermont’s Community Advisory Panel and similar bodies established in
other decommissioning reactor communities, do not take the place of
hearings.
THE DECOMMISSIONING PLAN SHOULD BE REINSTATED AND REPLACE THE PSDAR.
Under
the 1996 revision to the decommissioning regulations, the NRC also
eliminated the requirement that licensees submit a decommissioning plan.
Instead, licensees are only required to submit a Post-Shutdown
Decommissioning Activities Report (PSDAR) within two years of final
shutdown. The PSDAR is a brief document, lacking any meaningful detail
as to the methodology and site-specific plans, essentially conveying
that the licensee will figure it out as decommissioning proceeds. This
fundamental change has eliminated any meaningful level of transparency
and accountability for the conduct of decommissioning, allowing the
licensee to proceed in relative secrecy and without NRC oversight.
The
decommissioning plan must be a thorough guide and road map for the
cleanup process; it is an instrument to hold a licensee accountable for
the cleanup commitments it establishes in the plan. A 30 page narrative
or report (PSDAR) identifying the licensee’s actions does not qualify as
a plan and does not establish verifiable licensee commitments. The
rulemaking must reinstitute the requirement that licensees submit a
complete, thorough, and substantive decommissioning plan; and that NRC
review and approve the plan, and oversee its implementation.
NRC
MUST RESTRICT THE USE OF THE SAFSTOR DECOMMISSIONING OPTION AND REQUIRE
LICENSEES TO CHOOSE THE MOST PROTECTIVE DECOMMISSIONING METHOD TO
MINIMIZE THE EXPOSURE OF WORKERS AND THE PUBLIC TO RADIATION.
Existing
decommissioning rules permit licensees to select among three methods
for decommissioning at their sole discretion and without guidance as to
the particular hazards and considerations they may pose to worker and
public health and safety. DECON, or rapid dismantlement, involves
dismantling reactor facilities and disposing of radioactive waste within
just a few years after closure, while ambient radiation levels are
still quite high. This has resulted in occupational safety hazards and
contamination of workers; releases of radiation into the environment;
and higher levels of radioactivity being deposited in radioactive waste
dumps, as well as higher disposal costs.
SAFSTOR presents
increasingly problematic outcomes. Under SAFSTOR, the licensee may
exercise its discretion to defer decommissioning for an indeterminate
period of time, so long as it is completed with 60 years from the date
of closure. Licensees operating reactors in states with merchant power
markets, where the licensee is not a utility company and has no access
to rate making to pay for the cost of decommissioning, have opted for
SAFSTOR as their decommissioning method of choice. It appears this is
the case for two reasons: they have not continued to invest in the
decommissioning trust funds they acquired along with the reactors, and
they are seeking to defer liability for decommissioning fund shortfalls
indefinitely, as well as to take advantage of NRC exemptions for use of
the decommissioning fund. In addition, by delaying decommissioning for
sixty years, it is possible that the licensee or its parent company may
have declared bankruptcy or no longer exist, complicating NRC
enforcement of the license.
The lenient use of SAFSTOR makes
it possible for radioactive contamination onsite to spread unchecked, as
well as to complicate the eventual dismantlement of the reactor
facilities, due to structural degradation, corrosion, and animal
infestation of the facilities. Examination of licensees decommissioning
trust fund status reports, which include tables showing annual
decommissioning trust fund projections out to the projected license
termination dates, show that SAFSTOR is typically the most expensive
decommissioning method as expenditures for mothballing the site
accumulate over decades. The use of SAFSTOR must be justified and
require selection of the earliest possible decommissioning date. Along
with our above recommendations on decommissioning funding assurance and
exemptions for use of the decommissioning fund, this would mitigate some
of the worst outcomes that are possible under present regulations.
ENTOMB
is only appropriate under very specific circumstances under which
reactor facilities are too contaminated to be safely dismantled and/or
disposed of, for example, reactors that have had major accidents, such
as Chernobyl. The possibility that ENTOMB could be utilized for any
purpose other than as an option of last resort is unacceptable.
NRC SHOULD INCLUDE A FOURTH DECOMMISSIONING OPTION TO ENCOURAGE LICENSEES TO SELECT THE MOST PROTECTIVE APPROACH POSSIBLE.
NRC
should encourage licensees to select the most protective
decommissioning method possible by promulgating a fourth option. This
method would balance the risks of DECON and SAFTSTOR described above,
following one of the most successful reactor decommissionings to date:
the Rancho Seco reactor in California. Currently, licensees are
permitted to choose a combination of DECON and SAFSTOR, dismantling and
decontaminating some parts of the reactor site immediately and
postponing decommissioning of others until later.
NRC should
formalize a fourth method that establishes best practices for achieving
the objectives of decommissioning in a timely manner while minimizing
risk to workers and the public. This method would involve thorough
planning of decommissioning activities while attending to the most
immediate risks first (e.g., eliminating high-density storage of
irradiated fuel in spent fuel pools). Such an approach would also ensure
the retention of the skilled workforce’s training and institutional
knowledge, and it would enable decommissioning and site remediation to
be completed in a reasonable period of time. For instance, transfer of
irradiated fuel from high-density pool storage could occur in the first
five to seven years, while monitoring, site surveys and decommissioning
planning are conducted. Dismantlement and decontamination of the reactor
facilities could take place beginning afterward, reducing ambient
radioactivity levels before major dismantlement and decontamination
activities start, thereby reducing the risk to workers, the public, and
the environment. And site remediation could be completed within twenty
to twenty-five years of closure of the reactor, permitting license
termination in a reasonable period of time.
This
decommissioning option could be labeled Planned Decommissioning and Site
Remediation (PDSR). Rancho Seco’s owner, the Sacramento Municipal
Utility District, was able to complete decommissioning within about
twenty years, even though the decommissioning trust fund was underfunded
at the time it closed the reactor (1989). By approaching
decommissioning in roughly the fashion outlined above, SMUD was able to
accumulate funds for the most expensive parts of decommissioning, while
retaining a comparatively large percentage of the pre-existing
workforce.
NRC SHOULD PERMIT AGREEMENT STATES TO ADMINISTER AND OVERSEE DECOMMISSIONING.
The
outcome of decommissioning ultimately has the greatest impact on states
and local communities. They have a direct and long-term stake in the
issues most germane to the process, and they also tend to have oversight
of overlapping regulatory issues and standards that are outside of
NRC’s jurisdiction but which impact decommissioning activities, such as
remediation of non-radiological pollution (e.g., toxic chemicals like
PCBs). Certain reactor sites, like Yankee-Rowe, were able to complete
radiological decommissioning to NRC’s standards, but have severe
chemical contamination problems that have made it impossible for the
sites to be released for unrestricted use. NRC would retain authority
over certifying license termination, but permitting states to exercise
agreement state authority over the rest of the process, and to
promulgate their own rules per their agreement state authority, would
conserve NRC resources while providing states and the public a
beneficial and appropriate role in the process.
SITE-SPECIFIC
ADVISORY BOARDS SHOULD BE ESTABLISHED AS A FORMAL MECHANISM FOR LOCAL
AND STATE PARTICIPATION DURING DECOMMISSIONING.
It is
essential that the community in the effluent pathway of reactors as well
as states that have oversight responsibilities, including advocacy for
ratepayers, have the opportunity to participate in pollution reduction
and prevention during decommissioning. This participation must be
meaningful. The passive community participation in which limited
information is fed to citizens to allay their fears is ineffective.
Holding a meeting in a community to “inform” them of decommissioning is
inadequate. The Appellate Court rejected this approach in the
Yankee-Rowe case. A process must evolve which is responsive to the
concerns of affected citizens who will continue to bear the burdens of
long term exposure to low-level radiation and contamination. Citizens
must have a substantive role in decommissioning in order to clarify,
negotiate and protect their community’s interests and to satisfy the
requirements of a constitutional democracy.
Communities should
be given the opportunity to participate in decommissioning from its
onset. Therefore, we propose that Site-specific Advisory Boards be
offered to reactor communities as a formal mechanism of community
participation during decommissioning, since the process of site clean-up
could span decades if not lifetimes. These boards must be independently
convened in order to be effective. The Advisory Board would meet
regularly to give meaningful input into decisions concerning health and
safety, pollution prevention and reduction. The boards would function to
educate the community regarding the impacts of the technology that
exist in their neighborhood. They should include diverse interests such
as local government, public interest groups, representatives of towns in
the effluent pathway (including representatives from adjacent states),
tribal governments, reactor worker representatives, and Federal and
State regulators such as the NRC, public health and environmental
departments, etc. An ecology of democracy must develop for local
residents, scientists, technologists, industry, and regulators to work
together to solve the contamination problems inherent in the nuclear
fuel cycle. Costs for expert consultation should be borne by the
licensee, either by allocation from NRC or, in the case of agreement
state regulation as recommended herein, state regulatory authorities
with oversight of the decommissioning process.
THE PROPOSED RULEMAKING MUST ESTABLISH NRC INSPECTIONS AND ENFORCEMENT DURING DECOMMISSIONING.
NRC
currently provides no meaningful oversight and enforcement of
decommissioning activities. There are no resident inspection staff after
permanent shutdown of the reactor, and there are no regular inspections
during the decommissioning process. With no meaningful public
involvement, no hearing rights, and no detailed planning required for
decommissioning, the lack of NRC oversight means licensee compliance
with regulations is impossible to verify and enforce at all, much less
on a timely basis. NRC must provide for a meaningful oversight process
for decommissioning, including dedicated inspection staff with relevant
specialization and expertise, regular inspections and reporting,
substantive public information and engagement, and timely enforcement
mechanisms.
NRC MUST INCREASE ANNUAL LICENSE FEES FOR CLOSED REACTORS.
NRC
is required under federal law to collect fees from its licensees (and
license applicants) in amounts that total 90% of the agency’s annual
budget. Each year, NRC proposes a revised fee schedule to Congress and,
upon approval, updates 10 CFR Part 171 of its regulations. It has been
NRC practice to charge vastly reduced fees to reactor licensees during
decommissioning, and over the last few years, the gap between operating
and decommissioning reactor license fees has widened significantly. In
2013, operating reactor license fee was $4,390,000; the decommissioning
reactor license fee was only $231,000, or nineteen times less. In 2015,
the operating reactor license fee had risen nearly 15%, to $5,030,000,
but the decommissioning reactor license fee had actually decreased By
3.5%, to $223,000.
This clearly reflects the NRC’s oversight
and enforcement posture toward decommissioning. That must change not
only to better align the agencies priorities toward providing meaningful
oversight of decommissioning activities for the reasons detailed above,
but also to correct a conflict of interest in the lopsided fee
structure. In effect, NRC has provided a perverse incentive both to
devalue public health and safety issues involved in decommissioning and
site remediation and to enforce safety standards for operating reactors
less stringently.
On the one hand, by charging such small fees
for decommissioning reactors, NRC cannot justify devoting staff and
technical resources to decommissioning-specific issues that could better
inform its understanding of the needs and priorities for regulation and
enforcement. And on the other hand, because the agency takes such a
significant hit to its budget with each reactor that closes, it could
inculcate a culture within the agency that views enforcement of safety
regulations as a threat to the agency’s budget and the job security of
NRC staff.
This conflict must not be allowed to continue, and
NRC must ensure that it has adequate resources to provide greater
oversight and enforcement of decommissioning, particularly as more
reactors are closing and decommissioning becomes a more prevalent public
health and safety concern.
Sincerely,
Deb Katz
Executive Director
Citizens Awareness Network
P.O. Box 83
Shelburne Falls, MA 01370
Timothy Judson
Executive Director
Nuclear Information and Resource Service
6930 Carroll Ave., Suite 340
Takoma Park, MD 20912
Subscribe to:
Post Comments (Atom)
1 comment:
I have gone through the site and read all blogs and this is a nice one:
radiological decontamination and decommissioning
Post a Comment