Susquehanna Steam Electric Station
June 19, 2012 – Operators
at the Unit 1 reactor performed a planned shutdown to investigate the
source of a minor water leak inside the containment structure.
A
plant official said the leak does not affect the safety of the plant or
the public. Unit 2 is continuing to operate at full power.
May
7, 2012 – The NRC issued a report dealing with a supplemental inspection
at the Unit 1 reactor from Feb. 13 through March 2, 2012. The
inspection stemmed from unplanned scrams (plant shutdowns) in 2010 and
early 2011, and an internal flooding incident in the third quarter of
2010 that resulted in a white finding from the NRC of low to moderate
safety significance.