From CourierPostOnline.com:
Oyster Creek Generating Station employees will continue working on replacing underground pipes during a planned outage as part of the state's tritium remediation project.
The power plant entered its planned refueling outage program on Monday morning.
More than 5,000 gallons of water have been pumped to date as part of the remediation project. Exelon Corp., the owner and operator of the Forked River-based power plant, shut down the reactor at 12:01 a.m. for a scheduled refueling and maintenance outage.
According to a statement Monday from Exelon Communications Manager David Benson, throughout the outage, workers will perform approximately 9,500 activities on a variety of plant components and systems, including replacing both of the station's main transformers, as well as finishing the majority of a 16-month, $13.3 million project to move pipes containing tritium above ground or into monitored vaults.